A certain work was started by 4 men and 10 women who completed 50% of the work in 6 days . Then another 2 men and 2 women joined them and they could complete two-third of the remaining work in three days. How many men along with 6 women are required to complete the remaining work in two more days ?
Answers
Answer:
8 women are needed to finish the work.
Step-by-step explanation:
Remaining work time-and-work-q-65267.png 4 men + 10 women do 1 work in 12 days.
6 men + 12 women do 1 work in 9 days.
48 men + 120 women = 54 men + 108 women ⇒ 6 men = 12 women ⇒ 1 men = 2 women
∴ In 12 days 1 work requires 9 men
∴ In 1 day 1 work requires 9 × 12 men
∴ In 3 days 1 work requires time-and-work-q-65261.png
∴ In 3 days ⁴⁄₉ work requires time-and-work-q-65255.png men
There are 6 men and 12 women or (12 men equivalent)
So, 4 men equivalent is required additionally
∴ 8 women are needed to finish the work.
Time and Work
Given:
4 men and 10 women finishes 50% of the work in 6 days.
2 Men and 2 women joined them and covers two-third of remaining work in 3 days.
To find:
No. of men along with 6 women required to finish the remaining work in 2 extra days.
Explanation:
Let the work done by 1 men in 1 day be x.
Let the work done by 1 women in 1 day be y.
As per question,
we can write equation (i) as
On multiplying this with 3 , to use elimination method, it will,
On solving both (ii) and (iii),
Let the number of men required be p
Substituting the value of x and y, we get
Hence, the number of men required will be 6.