Physics, asked by Ajeshkm6029, 9 months ago

A clay 5 m thick in field takes 300 days to attain 50% consolidation with cindition of double drainage.If the same clay layer is underline by hard rock then the time taken to attain 50% consolidation will be

Answers

Answered by sahariamanjoy
0

Answer:

1200 days

Explanation:

Similar questions