A cobbler works 19/3 hours daily.how many hours does he work in a week?
Answers
Answered by
0
Answer:
Any worker day question can be solved with the concept of man-days.
As it takes 3 days for 10 workers to build a house. This implies a house needs 30 man-days to be built up.
Therefore, 4 houses will need 120 man-days.
Now, we have 15 workers.
Hence we would need 8 days (120/15) to build 4 houses.