Math, asked by lakshmi2ammuaish, 15 hours ago

A company is in the process of preparing a budget for launching a new product. The following table provides the associated activities and their durations. Construct the project network. Activity A : Forecast Sales Volume B : Study competitive market C : Design item and facilities D : Prepare production schedule E : Estimate cost of production F : Set sales price G : Prepare budget (b) Predecessor(s) — — A C D B, E E, F Explain PERT procedure. 3 Duration (days) 10 7 5 3 2 1 14​

Attachments:

Answers

Answered by anubhav3437
3

Answer:

option B study competitive market

Similar questions