a company planned to finish a project with 80 people in 80 days if after the the initial 10 days the number of people reduced to 70 by how many days will the project get delayed
Answers
Answered by
9
Answer:
10 days delay
Step-by-step explanation:
in ten day 12.5% work done by 80 peoples
then 87.5% work hsas to be done by 70 peoples
the days consoder as 'x'
then( 70/x)*100 = 87.5
1/x = 87.5/7000
x =7000/87.5
x =80
so 70 peoples take 80 days to finish the work
so 10 days delay