Math, asked by praveenchanduponguru, 14 days ago

A company was assigned a project for creating a railway link for a certain stretch in a difficult terrain, and it engaged 74 workers for the task. After the passage of 46% of the allocated time, construction of only 37% 2 13 of the stretch could be completed. How many more workers should be engaged, so as to enable the company to complete the project within the allocated time?​

Answers

Answered by adorablegenius1
0

Answer:

13

Step-by-step explanation: