Let say work = 1
75 % of work = (75/100) * 1 = 3/4
3/4 is done by A in 45 day
1 is done by A in = 45/(3/4) = 60 Days
Work done by A in 1 Day = 1/60
B is 25 % More efficient than A
so work done by B in 1 day = Work done by A + (25/100)*(workdone by A)
= 1/60 + (25/100)(1/60)
= 1/60 + 1/240
= (4 + 1)/240
= 5/240
= 1/48
A + B 's 1 day work = 1/60 + 1/48
= (4 + 5 )/240
= 9/240
A& B will complete the work in 240/9 days
= 26.67 Days