A complete a work in x day and B complete the same work in y days the number of days the will take to do the whole work together
Answers
Answered by
1
Answer:
UR ANS
MAKE MY ANS BRAINLIEST
Attachments:
Answered by
0
Step-by-step explanation:
no of days taken by A = x
efficiency of A = 1/x
no of days taken by B = y
efficiency of B = 1/y
total efficiency = 1/x + 1/y
= (x + y) /xy
days they need altogether = 1 / (x +y)