Math, asked by wwwbengao4718, 1 year ago

A complete work in 18 days and b in 30 days both started working and a quite after fews days ,after how many days a quite if work is complted in 20 days

Answers

Answered by spiderman2019
0

Answer:

4 days

Step-by-step explanation:

Rate of work by A = 1/18.

Rate of work by B = 1/30.

Let x be the days worked by A .

According to the question, we have that B works for all 20 days and A works only for 20 x days, thus

1/18 (20 - x )  + 1/30 * 20 = 1

(20-x)/18 = 1 - 2/3

20 - x = 18/3

20 - x = 6

x = 20 - 6 = 4 days.

Answered by BrainlyBAKA
0

"The rate of A 1/18 job per day;

"The rate of B 1/30 job per day.

"Say they need 20 days to complete the project.

"According to the stem we have that B works for all t days and A works only for 20-t days, thus 1/18*(20-t) + 1/30 *20 = 1

"t = 14 days

"HOPE IT HELPS

"PLEASE MARK ME BRAINLIEST ☺️