a completed 3/8th of a piece of work in 12 days.how many days will he take to complete the remaining work
Answers
Answered by
1
Answer:
Step-by-step explanation:
3/8th of the work in 12 days.
1/8th of the work in 12/3 = 4 days
8/8= total work in 4*8 = 32 days