Math, asked by blaiiirXD, 7 months ago

A completes 80% of work in 20 days. A and B together finish the remaining 20% of work in 3 days. How long would it take B alone to do the work?

Answers

Answered by shrutinemane1
2

Answer:

A completes 80% of a work in 20 days. Then B also joins and A and B together finish the remaining work in 3 days. How long does it need for B if he alone completes the work? Work done by A and B in 3 days = 20/100 = 1/5 (Because remaining 20% is done in 3 days by A and B)

Answered by ashauthiras
1

Answer:

B can complete the work in 75/2 days = 37 ½ days

Step-by-step explanation:

Work done by A in 20 days = 80/100 = 8/10 = 4/5

Work done by A in 1 day = (4/5) / 20 = 4/100 = 1/25 --- (1)

Work done by A and B in 3 days = 20/100 = 1/5 (Because remaining 20% is done in 3 days by A and B)

Work done by A and B in 1 day = 1/15 ---(2)

Work done by B in 1 day = 1/15 - 1/25 = 2/75

=> B can complete the work in 75/2 days = 37 ½ days

Similar questions