A Completes A Piece Of Work In 3/4 Of The Time In B Does,B Takes 4/5 Of The Time In C Does.They Got A Profit Of Rs.40000 How Much B Gets?
Answers
Answered by
0
if c takes 5 days to do work then
b will take 4 and a will take 3 as given in the question
now =if they work together then they will work in one day is (1/3+1/4+1/5)
now to complete that work they take x days then x(1/3+1/4+1/5)=1
now x=60/47
now in 60/47 days work done by B is 60/(47*4) = 15/47
now 15/47 th of profit 40000 is 12765
B's share is 12765.
Similar questions