. 'A' completes a work in 12 days. 'B' completes the
same work in 15 days. A started working along and
after 3 days B joined him. How many days will they
now take together to complete the remaining work?
(a) 6
(c) 5
(e) None of these
(b) 8
(d) 4
Answers
Answered by
2
Answer:
5
Step-by-step explanation:
for A = w /12
B = W/15
=w/12 ( 3+x)W/15x = w
=w/15 + x/15 =1
= 5