A completes a work in 8 days and B completes the same work in 10 days. find the number of days to complete the work, if they work together.
Answers
Answered by
48
Work done by A in 1 day = 1/8
Work done by B in 1 day = 1/10
Work done by A + B in 1 day = 1/8 + 1/10
=》 18/80
=》 9/40
Number of days required when A and B work together = 40/9
#BeBrainly
anisru:
nice sir
Answered by
34
Hey buddy...!! here is ur answer..
Given that.. A completes a work in 8 days
Then completes work in a day = 1/8
and B completes a work in 10 days
Then completes work in a day = 1/10
When they work together they complete work in a day = 1/10+1/8 = 18/80
Then they complete total work in 80/18 days
=> 80/18 = 40/9 = 4.4 days
I hope it will be helpful for you..!!
THANK YOU ✌️✌️
Given that.. A completes a work in 8 days
Then completes work in a day = 1/8
and B completes a work in 10 days
Then completes work in a day = 1/10
When they work together they complete work in a day = 1/10+1/8 = 18/80
Then they complete total work in 80/18 days
=> 80/18 = 40/9 = 4.4 days
I hope it will be helpful for you..!!
THANK YOU ✌️✌️