A construction site requires at least 5 labourers to get a job done in 12 days. how many days will it take if 12 labourers are hired for the same job
Answers
Answered by
2
Answer: 28
Step-by-step explanation:
Answered by
1
Step-by-step explanation:
5 labourers= 12 days
12 labourers= 12/5
=2.4 days