Math, asked by vijayagrawal641, 3 months ago

A construction site requires at least 5 labourers to get a job done in 12 days. how many days will it take if 12 labourers are hired for the same job​

Answers

Answered by monikashrivastav244
2

Answer: 28

Step-by-step explanation:

Answered by sukhvinder84
1

Step-by-step explanation:

5 labourers= 12 days

12 labourers= 12/5

=2.4 days