A constructor undertook a contract to complete a part of stadium in 9 months with a team of 560 persons. Later on it was required to complete the job in 5 months. How many extra person should he employ to complete the work?​

Answers

Answered by sabalsharma
3

Answer:

600 people  should me employ

Step-by-step explanation: