Math, asked by mks808385, 5 months ago

a construstion company employees 300 men to build a foot - over bridge in 24 days . after 10 days , it's gets 50 more men to work. In how many days will the remaining work be completed.

Answers

Answered by baron15912
1

Answer:

Total work = 210 x 60 = 12600 mandays.

Work finished in 12 days = 12600 x 12/60 = 2520 mandays

Remaining work = 12600 - 2520 = 10080 mandays

Number of men now = 210 + 70 = 280

Number of days required = 10080/280 = 36 days.

Step-by-step explanation:

Similar questions