Math, asked by gopinagu4715, 11 months ago

A contarctor undertakes to make a road in 40 days and employe 25 men. Aftsr 24 days he finds that only one third of the road is made. How many extra men xshould he employee so that he is able to complete the work 4 days earlier

Answers

Answered by amitnrw
0

Answer:

75 men

Please mark the answer as "The Brainliest answer" if you like it

Step-by-step explanation:

Let say w is the work to be done

25 men worked for 24 days and completed 1/3 of work

25 * 24 = w/3

w = 1800  mandays

pending work = w - w/3 = 2w/3 = 2*1800/3 =  1200 mandays

work to be completed 4 days earlier so 40-4 = 36 days

24 days already gone so remaining days

= 36-24 = 12 days

men required = 1200/12 = 100

25 men were already working

so additional men required = 100-25  = 75


Similar questions