Math, asked by afras4969, 1 year ago

A contract is to be completed in 56 days and 104 men are set to work, each working 8 hours a day. After 30 days, 2/5th of the work is finished. How many additional men may be employed so that work may be completed on time, each man now working 9 hours per day?

Answers

Answered by sprao534
6
Please see the attachment