Math, asked by adityagour77, 1 month ago

A contract on constructing job specifies a penalty for delay of completion beyond a certain date as follows : ` 15 for first day, ` 25 for second day, ` 35 for third day etc. The penalty for each succeeding day being ` 10 more than the preceding day. How much money the contractor has to pay as penalty. If he has delayed the work by 25 days?​

Answers

Answered by gs7729590
1

Answer:

A contract on constructing job specifies a penalty for delay of completion beyond a certain date as follows : ` 15 for first day, ` 25 for second day, ` 35 for third day etc. The penalty for each succeeding day being ` 10 more than the preceding day. How much money the contractor has to pay as penalty. If he has delayed the work by 25 days?

["Ans = Therefore, the contractor has to pay Rs 27750 as penalty.]"

Answered by nihanthyepuri9
1

Rs . 27750

Please don't forget to make me the brainliest and please thank for my answer