A contract on construction job specifies a penalty for delay of
completion beyond a certain date as follows:
Rs 200 for the first day, Rs 250 for the second day, Rs 300 for the
third day, etc.
The penalty for each succeeding day being Rs 50 more than for
the preceding day.
(i) How much money the contractor has to pay as penalty, if he
has delayed the work by 30 days ?
(ii) Which mathematical concept is used in the above problem ?
(iii )Which value should be promoted in this problem ?
Answers
Answered by
3
Answer:
Please have a look on attachment...
Hope this helps!