A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rupees 200 for the first de rupees 254 2nd a rupees 300 for the third day etc. penalty for each succeeding day being rupees 50 more than for the preceding day how much money the contractor has to pay penalty if he has delete the work by 30 days.
Answers
Answered by
0
Answer:
a contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day, Rs 300 for the third day,etc.. the penalty for each succeeding day being Rs 50 more than for the preceeding day.