a contract on construction job specifies a penalty for delay of completion beyond a certain date as follows rupees 200 for the first day rupees 250 for the second year rupees 300 for the third day the penalty for succeeding day being Rs 50 more than the preceding day how much money the contractor has to pay as penalty if we delete the work by 30 days
Attachments:
Answers
Answered by
19
♡●BONJOUR●♡
⬇️HERE IS YOUR ANSWER⬇️
________________________
REFER ATTACHMENT
HOPE THIS ANSWER HELPS YOU
MARK AS BRAINLIEST ✌✌
_______×××××_______
Attachments:
angel1238:
thnkuhhh so much ☺☺☺☺
Answered by
9
Answer:
Rs 27750
Step-by-step explanation:
The contract specifies penalty of Rs 200 the first day .
The next day penalty is Rs 250 .
Image this as an A.P or arithmetic progression .
a = Rs 200 .
d = Rs 50
n = 30 .
Sn = n/2 [ 2 a + ( n - 1 ) d ]
⇒ Sn = 30/2 [ 2 ( 200 ) + ( 30 - 1 ) ( 50 ) ]
⇒ Sn = 15 [ 400 + 29 × 50 ]
⇒ Sn = 15 [ 400 + 1450 ]
⇒ Sn = 15 [ 1850 ]
⇒ Sn = 27750 ,
The money will be Rs 27750 .