Math, asked by BrainlyHelper, 1 year ago

A contract on construction job specifies penalty for delay of completion
beyond a certain date as follows:Rs.200 for the first day,Rs250 for
the second day,Rs.300 for the third day,etc.,the penalty for each succeeding
day being Rs.50 more that for preceding day.

(i)How much money the contractor has to pay a penalty,if he has delayed
the work by 30 days?
(ii)Which Moral Value One Can Learn From Above Problem?
(class 10 CBSE SAMPLE PAPER 2017-18 MATHS)

Answers

Answered by nikitasingh79
3
Given:


Penalty  for first day= 200

Penalty for second day = 250

Penalty for third day = 300

Every day penalty increase = 50

It forms an arithmetic series(A.P).

The Required sequence is 200, 250, 300, 350…..

Now

first term (a )= 200

common difference( d )= 50

number of terms(n) = 30 (penalty for 30 days)

Sn = (n/2) {2a + (n-1)d}

    = (30/2){2×200 + (30-1)×50}

    = 15×(400 + 29×50)

   = 15×(400 + 1450)

    = 15×1850

Sn = 27750

Hence,  total penalty for 30 days = ₹ 27750



Value- One should be punctual and hardworking to his work and show dedication for his work.