A contract on construction job specifies penalty for delay of completion
beyond a certain date as follows:Rs.200 for the first day,Rs250 for
the second day,Rs.300 for the third day,etc.,the penalty for each succeeding
day being Rs.50 more that for preceding day.
(i)How much money the contractor has to pay a penalty,if he has delayed
the work by 30 days?
(ii)Which Moral Value One Can Learn From Above Problem?
(class 10 CBSE SAMPLE PAPER 2017-18 MATHS)
Answers
Answered by
3
Given:
Penalty for first day= 200
Penalty for second day = 250
Penalty for third day = 300
Every day penalty increase = 50
It forms an arithmetic series(A.P).
The Required sequence is 200, 250, 300, 350…..
Now
first term (a )= 200
common difference( d )= 50
number of terms(n) = 30 (penalty for 30 days)
Sn = (n/2) {2a + (n-1)d}
= (30/2){2×200 + (30-1)×50}
= 15×(400 + 29×50)
= 15×(400 + 1450)
= 15×1850
Sn = 27750
Hence, total penalty for 30 days = ₹ 27750
Value- One should be punctual and hardworking to his work and show dedication for his work.
Penalty for first day= 200
Penalty for second day = 250
Penalty for third day = 300
Every day penalty increase = 50
It forms an arithmetic series(A.P).
The Required sequence is 200, 250, 300, 350…..
Now
first term (a )= 200
common difference( d )= 50
number of terms(n) = 30 (penalty for 30 days)
Sn = (n/2) {2a + (n-1)d}
= (30/2){2×200 + (30-1)×50}
= 15×(400 + 29×50)
= 15×(400 + 1450)
= 15×1850
Sn = 27750
Hence, total penalty for 30 days = ₹ 27750
Value- One should be punctual and hardworking to his work and show dedication for his work.