A contract to build a house in 30 days. He employed 10 men to build the house. After 20 days, they completed only 1/3 of the total work. How many more men will be required to finish the remaining work within due time?  ​

Answers

Answered by kbasamma46
0

Answer:

I not get answers

woven cshsgsbxbmskxkxnnx

Answered by Anonymous
0

Step-by-step explanation:

A contract to build a house in 30 days. He employed 10 men to build the house. After 20 days, they completed only 1/3 of the total work. How many more men will be required to finish the remaining work within due time?  