A contract was to be completed in 20 days and 24 men were put to work. After 13 days, 4 more men were engaged and the work was completed just in time. Had
not the extra men been engaged how many days would
the work have taken ?
(a) 23 (b) 25 (c)21 (1/6) (d) 21(1/3) (2) None
Answers
Answered by
2
Answer:
ans is 21 1/6
Step-by-step explanation:
24 men in 20 days
after 13 days
24+4= 28 men worked for 20-13=7 days
if 28 men in 7 days means 24 men in
28*7/24=8.16667
if extra men had not engaged then
13+8.16667= 21.16667 which is option c) 21 1/6 days
Answered by
1
Answer:
21 days extra will be needed if the extra men would not have been engaged.
Explanation:
We know that,
24 men are supposed to complete a work in 20 days.
After 13 days,
Total number of men = 24+4= 28
Number of days left = 20-13 = 7 days
∴ By applying the unitary method,
Total number of days = 8.16
∴ Work done by 24 men = 13+8.16 days = 21.16 days = 21 days
Answer) The men would need 21 days to complete the work, hence option C is the correct answer.