Math, asked by bdkdkd, 1 year ago

a contracter takes a contract of makeing 1000m long wall in 50days . in the end of 27 days he find only 448m of wall when he used 56 workers . now how many more workers he need to find the wall built in correct days

Answers

Answered by axelblaze
0
i think 64 workers is correct