A contracter undertakes to make a road in 40 days and employes 25 men. After 24 days he find only one third hiw many extramen should he employe so that he he is able to complete the work 4 days at laour.
Answers
Answered by
0
Solution 1
25 men can complete 13
work in 24 days
Suppose x men can complete 23 work in 12 days
25×2413=x×1223 25×24=x×122 x=100
Required extra men =100−25=75
Solution 2
25 men can complete 13 work in 24 days
=> 25 men can complete 23 work in 48 days
=> 25×4=100 men can complete 23 work in 484=12 days
Required extra men =100−25=75