Math, asked by SriKanishK6898, 1 year ago

A contractor agreeing to finish a work in 150 days, employed 75 men each working 8 hours daily. After 90 days, only 2/7 of the work was completed. Increasing the number of men by _____ and each one is working now for 10 hours daily, the work can be completed in time.

Answers

Answered by rathoresujal237
1

12 days may this help you