A contractor agrees to lay a road 3000m long in 30 days. 50 Men are employed and they work for 8 hours a day. After 20 working days, he finds that only 1200 m of the road is completed. How many more men does he need to employ in order to finish the project on time if each man now works 10 hours a day?​

Answers

Answered by dtdasun365
1

Answer:

he need extra 70 mens to complete project on time

Step-by-step explanation:

  1. (50×20×8)+(y×10×10)=20000 (y= men)
  2. y=120
  3. y=50+70
  4. need men=70