A contractor consented to complete a construction work in 96 days
and engaged 100 labourers for that purpose. But he observed only
1/7th of the work was done in 1/6th of the schedule time. How many
additional labourers will be required to complete the work in time?
Answers
Answered by
2
Step-by-step explanation:
Let the work be = 1
thus,
1/7 work takes 96/6 days by taking 100 labourers
1/7 Work takes 16 days by taking 100 labourers
100 labourers will take 7 X 16 days to complete the work.
100 X 7 X 16 labourer will take 1 day. to complete the work.
11200/96 labourers will take 96 days to complete the work.
116 labourers will take 96 days to complete the work
therefore,
116-100=16 additional labourers will be required to complete the work.
Similar questions