A contractor contract to build a house in 30 days. He employed 10 men to build the house. After 20 days, they completed only 1/3 of the total work. How many more men will be required to finish the remaining work within due time?
Answers
Answered by
2
Answer:
You have to multiply the no.of workers by 4 to get the final answer.
So, no.of required workers = 10×4 = 40