Math, asked by muddasirkhanpst2017, 1 month ago

A contractor contract to build a house in 30 days. He employed 10 men to build the house. After 20 days, they completed only 1/3 of the total work. How many more men will be required to finish the remaining work within due time?​

Answers

Answered by prajithnagasai
2

Answer:

You have to multiply the no.of workers by 4 to get the final answer.

So, no.of required workers = 10×4 = 40

Answered by mn358229
0

Step-by-step explanation:

(Units: 1 - 4)

Q.1 A contractor contract to build a house in 30 days. He employed 10 men to build the house. After 20 days, they completed only 1/3 of the total work. How many more men will be required to finish the remaining work within due time? (20) (Units:

Similar questions