Math, asked by oeowkow, 4 months ago

A contractor decided to complete the work in 90 days and employed 50 men at the beginning and 20 men additionally after 20 days and got the work completed as per schedule. If he had not employed the additional men,how many extra days would he have needed to complete the work?​

Answers

Answered by Anonymous
4

QUESTION:-

A contractor decided to complete the work in 90 days and employed 50 men at the beginning and 20 men additionally after 20 days and got the work completed as per schedule. If he had not employed the additional men,how many extra days would he have needed to complete the work?

SOLUTION:-

50 men have already worked for 20 days and completed a part of the work. 

If the remaining work is done by 70 men (50 + 20  = 70), the work can be completed in 70 days and the total work can be completed

in 90 days as per the schedule.   

Let "x" be the no. of days required when the remaining work is done by 50 men.

For the remaining work, 

70 men -------- > 70 days

50 men -------- > x days

The above one is a inverse variation.

Because, when no. of men is decreased, no. of days will be increased.

By inverse variation, we have

70 ⋅ 70  =  50 ⋅ x

4900  =  50x

98  =  x

So, if the remaining work is done by 50 men, it can be completed in 98 days.  

So, extra days needed  =  98 - 70  =  28 days.

Answered by sharma946529kks
1

Answer:

28 days is answer

Step-by-step explanation:

progess is upper side ans 1

Similar questions