A contractor employed 150 workers to finish a piece of work in a certain fixed number of days. on the first day all 150 worked, he dropped four workers on the second day, four more workers were dropped on the third day and so on. In this way, eight extra days are required to finish the work. Find the no. of days in which the work was completed ultimately.
Answers
Answered by
51
Number of days is 25
Attachments:

Answered by
27
Hope this helps you
I think this is correct