a contractor employed 210 men to build a house in 60 days after 12 days he joined 70 model men in how many days the remaining work will be finished?
Answers
Answered by
0
Answer:
In 28 days the remaining work will me finished.
Thank you..
follow me
Answered by
2
Answer:
28 days
Step-by-step explanation:
the remaining work will be finished in 28 days