Math, asked by Akshay11111111, 1 year ago

A contractor employed 210 men to build a house in 60 days.After 12 days,he was joined by 70 more men.In how many days will the remaining work be finished?

Answers

Answered by Ananyaaaaaaa
62
no.of days 210 men will take to finish remaining work=60-12=48
no.of days 280 men will take to finish the work=48*210÷280
=36days

Ananyaaaaaaa: hope this will help
Ananyaaaaaaa: if so plz mark my answer the brainliest
Akshay11111111: thanx
Answered by windyyork
25

Answer: The remaining work will be done in 36 days.

Step-by-step explanation:

Since we have given that

Number of men = 210

Number of days = 60

After 12 days,

Difference of days = 60-12 = 48

Number of more men = 70

We will use "Time and work":

210M\times 48=280M\times x\\\\3M\times 48=4M\times x\\\\3\times 12=x\\\\36=x

Hence, the remaining work will be done in 36 days.