A contractor employed 210 men to build a house in 60 days. After 12 days, he was joined by
70 more men. In how many days will the remaining work be finished?
Answers
Answered by
10
Traditional Method
Total work = 210 x 60 = 12600 mandays.
Work finished in 12 days = 12600 x 12/60 = 2520 mandays
Remaining work = 12600 - 2520 = 10080 mandays
Number of men now = 210 + 70 = 280
Number of days required = 10080/280 = 36 days.
Smart Method
Work done initially = 12 days
Days remaining = 48 days.
Increase in manpower = 70 men = 1/3
If 1/3rd manpower increase, then 1/(1+3)th time will decrease.
=> Decrease in time= 48 x 1/4 = 12 days
=> Work will be completed in 36 days.