A contractor employed 210 men to build a house in 60 days. After 12 days, he was joined
by 70 more men. In how many days will the remaining work be finished
good answer be tagged
Answers
Answered by
2
Answer:
no.of days 210 workers will finish the remaining work is 60-12 equal to 48
no.of days 280 people will finish the work is equal to
48*210/280= 36 days
36 days would be taken by 280 workers to complete the work
Answered by
0
Answer:
In how many days will the remaining work be finished 38 days