A contractor employed 210 men to build a house in 60 days. After 12 days, he was joined

by 70 more men. In how many days will the remaining work be finished
good answer be tagged​

Answers

Answered by savitay794
2

Answer:

no.of days 210 workers will finish the remaining work is 60-12 equal to 48

no.of days 280 people will finish the work is equal to

48*210/280= 36 days

36 days would be taken by 280 workers to complete the work

Answered by jayahaniswar
0

Answer:

In how many days will the remaining work be finished 38 days