Math, asked by Ethan1556, 1 year ago

A contractor employed 210 men to build ahouse in 60 days. after 12days, he joined by 70 more men. in how i how many days will the reaminingwork be finished

Answers

Answered by pramilajk5009
173

210 men can complete the remaining work in 48 days

So,we have to find out how many days 280 men can do (210+70 more men)

=210×48/280

=36

Therefore 280 men can complete the remaining work in 36 days.

Answered by Anonymous
3

Given:

  • 210 men were employed to build a house in 60 days.
  • After 12 days, 70 more men were added.
  • Total work done = 1

To Find:

  • Time taken to finish remaining work.

Solution:

  • Each man working for one day = \frac{1}{210*60}
  • After 12 days,
  • Total work done by 210 men in 12 days =  \frac{1}{210*60}*210*12 = \frac{12}{6} = \frac{1}{5}
  • When 70 workers were added after 12 days, the total workers = 210+70 = 280 workers.
  • Finding the remaining work to know the days required.
  • Remaining work = 1-1/5 = 4/5 → (1)
  • let the remaining work be completed in the next "X" days.
  • To find "x", consider total work done by 280 workers = \frac{1}{210*60} *280*X → (2)
  • Equating (1) and (2),
  • \frac{4}{5} = \frac{280X}{12600}
  • ⇒ 1400X = 50400
  • ⇒ X = 50400/1400 = 36 days.

∴Time taken to finish the remaining work by 280 workers is 36 days.

Similar questions