A contractor employed 210 workers to unload goods from a ship in 18 days. After 4 days it was found that only 1/6 part of the work was done. how many more men should be employed to finish the work in the time?
Answers
Answered by
0
Given:
A contractor employed 210 workers to unload goods from a ship in 18 days.
To find:
how many more men should be employed to finish the work in the time
Solution:
We have given the situation of the question as:
After 4 days it was found that only 1/6 part of the work was done
so with the same efficiency
The total work will be done by 210 workers in 24 days
Let the X number of workers is required to complete the work on time.
So, by the MDH formula, we get the number of the workers to complete the remaining works as:
- 210×20 = X×14
- X = 210×20/14
- X = 300
so,
90 workers should be employed to finish the work in the time
Similar questions