A contractor employed 210 workers to unload goods from a ship in 18 days. After 4 days it was found that only 1/6 part of the work was done. How many more men had to be employed to finish the work in time?

Pls answer properly. Do not answer absurd things or else i will report

Answers

Answered by dkchakrabarty01
0

Answer:

1/6 work is done, so 5/6 work is left

In 18 days 1 work is done by 210 men

In 1 day 1 work will be done by 210×18 men

In 1 day 5/6 work will be done by 210×18×5/6 men

In 14 days 5/6 work will be done by 210×18×5/(6×14) = 225 men.

So he has to employ 225 - 210 = 15more men