Math, asked by kalbandehanuman655, 5 months ago

A contractor employed 30 men to complete a piece of work in 20 days. If
he has to complete the work in 15 days, how many more men should he
employ?

Answers

Answered by smrit105
15

Answer:

The work requires 30 men x 20 days = 600 man-days.

In order to complete the same work in 15 days he needs 600 man-days/15 days = 40 men.

Since he already has 30 men he should engage 10 extra men to complete the work on time.

Answered by barickmanju12
7

Answer:

this is your answer

Step-by-step explanation:

hope it helps