Math, asked by manishaawale179, 4 months ago

A contractor employed 30 men to complete a piece of work in 20 days. If he has to complete
the work in 15 days, how many more men should he employ? (1) 50 (2) 40 (3) 30 (4) 10​

Answers

Answered by rudrakshasahu123
6

Answer:

This should be simple:

Work load = Work done

Let x=additional men to finish the job

Assuming same work rate of 8hrs per day, thus, you can equate:

(30)(20) = (15)(30+x)

x=10 men

Answered by Anonymous
0

Answer:They finished 5/6 of the work in 100 days. Due to rain the work stopped for 20 days and also destroyed 2/5 of the work. After rain 150 workers came to the work.

Step-by-step explanation: