Math, asked by Nikku2262, 8 months ago

a contractor employed 30 men to complete the project in hundred days but later on he realised that I just after 25 days on the 20% of the work has been completed how many extra days then the schedule time are required?
a)75day
b)100day
c)20 day
d)30 day
e)25day​

Answers

Answered by rubi2414
1

Answer:

c is the correct answer

for any explanation please inform

thankyou

have a good day