a contractor employed 30 men to complete the project in hundred days but later on he realised that I just after 25 days on the 20% of the work has been completed how many extra days then the schedule time are required?
a)75day
b)100day
c)20 day
d)30 day
e)25day
Answers
Answered by
1
Answer:
c is the correct answer
for any explanation please inform
thankyou
have a good day
Similar questions