Math, asked by neelimamaity05, 1 year ago

A contractor employed 30 men to do a piece of work in 38 days.After 25 days . he employed 5 men more and the work finished one day earlier. How many days he would have been behind , if he had not employed additional men?

Answers

Answered by leninviki
43
work=day*worker

Total work=30*38=1140

25 day work done=25*30=750

35 work done in 12 days=35*12=420

full done by both 30 +5 worker=750+420=1170

1170-1140
=30
work=day×worker
30=30×day
day=1

it's take one day more