A contractor employed 30 men to do the project in 100 days. But later on he realised that just after 25days only 20% of the work had been completed. How many extra days, than the scheduled time are required?
Answers
Answered by
3
Answer: 25 days
Step-by-step explanation:
20% work done in 25 days
100% work done = ?
Let, no. days required to complete whole work be 'x'
⇒20/25 = 100/x
⇒20*x = 100*25
⇒x = 100*25/20
⇒x = 100*5/4
⇒x = 25*5
⇒x = 125 days
no. of extra days required = 125-100= 25 days
I hope it helps (: