Math, asked by smansoor44081, 1 year ago

A contractor employed 35 with a target to do a piece of work in 37 days. after 20 days, he employed 10 more men and the work was finished 3 days earlier. how many days he would have been behind, if he had not employed additional men?

Answers

Answered by MarvelEdge17
1

Answer:

1 day

Step-by-step explanation:

35 men employed to finish a piece of work in 37 days.

After 20 days 10 more men were employed, so 45 men started working.

1. Time left to finish the work was 37-20 = 17 days.

2. Time taken to finish the remaining piece of work by 45 men was 17-3=14 as they finished the work 3 days earlier.

3. So if 45 men take 14 days to finish a certain piece of work, for 35 men to complete the same piece of work would require 45*14/35 = 18 days.

As 17 days were left to finish the work (as calculated in step 1 above), had the extra men were not employed, the contractor would have finished the work 18-17=1 day behind schedule.