A contractor employed 40 workers to finish a piece of work in 20 days.he found that the workers had completed only one-fourth of the work in 8 dats.how many additional workers should he employ so that the remaining work would be completed in the stipulated time?

Answers

Answered by haridasan85
7

Answer:

Workers days. work

40. 20. ....

40. 8. 1/4

x.... 12. 3/4

x is total workers required

x = (3/4)/I/4x8/12x40=80

totalworkers required x = 80

Addl workers 80-40=40