a contractor employed 40 workers to finish work in 20 days he found that the workers had completed olnly one - fourth of work in 8 days. How many additional worker should he employ so that the remaining work will be completed in stipulated time?
Step by step explanations required....
Answers
Answered by
0
Answer:
10
Step-by-step explanation:
Total Worker day= 40×20=800
1/4 work done i.e. 800×1/4=200
so remaining worker day = 600
remaining days=12
therefore total worker required 600÷12=50
Hence, additional worker required is 50-40=10
correct if wrong, I'm still learning.