A contractor employed 50 men to complete the project in 100 days. but later on he realised that just after 25 days only 20% of the work had been completed. how many extra days, than the scheduled time are required?
Answers
Answered by
0
Is to require 35 day to complete this task
Answered by
1
if in 25 days 20% complete then in 75 days 100%